Hopkins Landing Renovation

Share Hopkins Landing Renovation on Facebook Share Hopkins Landing Renovation on Twitter Share Hopkins Landing Renovation on Linkedin Email Hopkins Landing Renovation link

April 24, 2025 - Hopkins Landing Dock Project – Float Update

When the Hopkins Landing Dock was closed, the float was removed and placed into storage. Repairs were identified as part of the renovation project. Recently, upon closer inspection, it was discovered that the float was in significant disrepair and could not be reused. This replacement will require a separate design and construction contract and will not be completed alongside the main dock upgrades, which are expected to proceed in the early fall.


Background

Closed for safety, Hopkins Landing is now slated for renovation. A public engagement process took place in April through May, 2024. Construction is began in January 2025.

This is your space to learn about the project.

On the right

Read the summary of feedback from community engagement events held earlier this year.
Background to the project
Project timeline
Design concepts
Presentation provided at the open house


April 24, 2025 - Hopkins Landing Dock Project – Float Update

When the Hopkins Landing Dock was closed, the float was removed and placed into storage. Repairs were identified as part of the renovation project. Recently, upon closer inspection, it was discovered that the float was in significant disrepair and could not be reused. This replacement will require a separate design and construction contract and will not be completed alongside the main dock upgrades, which are expected to proceed in the early fall.


Background

Closed for safety, Hopkins Landing is now slated for renovation. A public engagement process took place in April through May, 2024. Construction is began in January 2025.

This is your space to learn about the project.

On the right

Read the summary of feedback from community engagement events held earlier this year.
Background to the project
Project timeline
Design concepts
Presentation provided at the open house

Have a question about the project? Ask it here.

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Has a contract been awarded for the Hopkins dock? We watch so many boats arrive with nowhere to dock. Many try to pull up on shore which doesn’t go so well. As of July 10, 2025, when are repairs slated to start and finish by on Facebook Share Has a contract been awarded for the Hopkins dock? We watch so many boats arrive with nowhere to dock. Many try to pull up on shore which doesn’t go so well. As of July 10, 2025, when are repairs slated to start and finish by on Twitter Share Has a contract been awarded for the Hopkins dock? We watch so many boats arrive with nowhere to dock. Many try to pull up on shore which doesn’t go so well. As of July 10, 2025, when are repairs slated to start and finish by on Linkedin Email Has a contract been awarded for the Hopkins dock? We watch so many boats arrive with nowhere to dock. Many try to pull up on shore which doesn’t go so well. As of July 10, 2025, when are repairs slated to start and finish by link

    Has a contract been awarded for the Hopkins dock? We watch so many boats arrive with nowhere to dock. Many try to pull up on shore which doesn’t go so well. As of July 10, 2025, when are repairs slated to start and finish by

    Jackie asked about 1 month ago

    Hello Jackie, a construction contract was awarded in late November of last year. Construction was to begin in January of this year, however it was postponed until August, 2025. This news release explains the reason for the delay.

Page last updated: 17 Jul 2025, 02:33 PM