January 2025 - Update

Due to permitting delays, Hopkins Landing Dock project has been delayed until late summer.

Following an updated biophysical assessment of the marine habitat completed in late-January, it was determined that further planning is required to protect eelgrass and fish habitat during construction. Site-specific measures must be developed to avoid harming these important ecological areas.

As a result, the necessary permits to proceed with construction within the permitted in-water works timeframe required by the Fisheries Act and Species at Risk Act cannot be secured. With the in-water works window closing at the end of January, construction cannot move forward until it reopens in mid-August at the earliest.

Read more by clicking here.



Background

Closed for safety, Hopkins Landing is now slated for renovation. A public engagement process took place in April through May, 2024. Construction is began in January 2025.

This is your space to learn about the project.

On the right

Read the summary of feedback from community engagement events held earlier this year.
Background to the project
Project timeline
Design concepts
Presentation provided at the open house


January 2025 - Update

Due to permitting delays, Hopkins Landing Dock project has been delayed until late summer.

Following an updated biophysical assessment of the marine habitat completed in late-January, it was determined that further planning is required to protect eelgrass and fish habitat during construction. Site-specific measures must be developed to avoid harming these important ecological areas.

As a result, the necessary permits to proceed with construction within the permitted in-water works timeframe required by the Fisheries Act and Species at Risk Act cannot be secured. With the in-water works window closing at the end of January, construction cannot move forward until it reopens in mid-August at the earliest.

Read more by clicking here.



Background

Closed for safety, Hopkins Landing is now slated for renovation. A public engagement process took place in April through May, 2024. Construction is began in January 2025.

This is your space to learn about the project.

On the right

Read the summary of feedback from community engagement events held earlier this year.
Background to the project
Project timeline
Design concepts
Presentation provided at the open house

Have a question about the project? Ask it here.

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
Page last updated: 29 Jan 2025, 01:35 PM