Project History
Project is moved to Connor Park
The results of the community check-in survey are provided to the SCRD Board. The Board vote to move the project to Connor Park and to retain some budget for upgrades to Coopers Green Park. The Board also asks staff to investigate whether or not the current hall at Coopers Green can be retained.
Community check-in on hall location
The SCRD launches a community check-in survey with options to keep the hall at Coopers Green or to move the project to Connor Park.
Project at Coopers Green halted
Project is halted due to a new expert report which outlines the potential for sea level rise to impact the building at the proposed location. The report recommends raising the hall an additional 1.5 metres.
Re-estimated project cost
Project cost is re-estimated at $4.5 million. SCRD Board approves additional budget to ensure further work could be done on design and technical assessments.
Project budget approved
The SCRD Board includes the budget for the hall construction in the financial plan in at $3.08 million. This allows the SCRD to begin some of the design & technical work involved with the project.
Grant approved - $2 million
The SCRD receives a two-million-dollar grant through the Investing in Canada Infrastructure Program (ICIP). This grant is due to expire on March 31, 2025.
Construction budget - $3 million
A construction budget of $3 million is presented to the SCRD Board. A grant application is also submitted