The Sunshine Coast Regional District (SCRD) is working to establish a service for the Pender Landing Wastewater Treatment Plant. This webpage is the hub for residents to learn more about the project and ask questions.
Background
The Pender Landing Wastewater Treatment Plant (WWTP) was designed and constructed in 2007 by the initial developer. The current system consists of collection system (sanitary sewer mains), WWTP facility and land disposal on Lot 41, with Lot 9 as a reserve field.
After construction of the WWTP was complete, the original developer pursued and acquired ownership of an existing ocean outfall as an alternative option to land disposal. In 2021, the SCRD Board directed staff to explore the feasibility of operation and ownership of the Pender Harbour Landing sewage ocean outfall. In 2026, the SCRD Board directed staff to initiate a Petition process to establish a local area wastewater service area that includes both the WWTP and ocean outfall.
The SCRD has been providing staffing support for the operation and maintenance of the WWTP, but must establish a formal service area in order to fund the operating and future capital costs of the WWTP.
This is your space to
Read reports related to the system See answers to commonly asked questions Read background information and preliminary costs for the service Ask questions about the service
The Sunshine Coast Regional District (SCRD) is working to establish a service for the Pender Landing Wastewater Treatment Plant. This webpage is the hub for residents to learn more about the project and ask questions.
Background
The Pender Landing Wastewater Treatment Plant (WWTP) was designed and constructed in 2007 by the initial developer. The current system consists of collection system (sanitary sewer mains), WWTP facility and land disposal on Lot 41, with Lot 9 as a reserve field.
After construction of the WWTP was complete, the original developer pursued and acquired ownership of an existing ocean outfall as an alternative option to land disposal. In 2021, the SCRD Board directed staff to explore the feasibility of operation and ownership of the Pender Harbour Landing sewage ocean outfall. In 2026, the SCRD Board directed staff to initiate a Petition process to establish a local area wastewater service area that includes both the WWTP and ocean outfall.
The SCRD has been providing staffing support for the operation and maintenance of the WWTP, but must establish a formal service area in order to fund the operating and future capital costs of the WWTP.
This is your space to
Read reports related to the system See answers to commonly asked questions Read background information and preliminary costs for the service Ask questions about the service
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends